Environmental Impact Report _CMN_PDF_ALT Print _CMN_EMAIL_ALT

A chronological summary of events of  the process of obtaining environmental decision for the project: Construction of   Kielce Airport,   located in the area of Obice in the Moarawica Commune and also Grabowiec in the Chmielnik Commune.  

10.08.2009

Application for the environmental decision to the Regional Director of Environmental Protection in Kielce

14.09.2009

Receiving the first comments on the  environmental impact report from the Regional Director of Environmental Protection in Kielce.

22 .09.2009

Submission of additional materials and information

19.11.2009 & 28.12.2009

The next comments of the Regional Director on the report.

01.2010 ÷ 04.2010  

Elaborating of the complement  to the report.

12.05.2010 

Submission of the complete report to the  Regional Director of Environmental  Protection.

17.08.2010

Obtaining next comments from  the Regional Director regarding the content of the report.

18.10.2010

Elaborating of the supplement  to the report and submission  to the Regional Director.

17.12.2010

Meeting of the Regional Commission for environmental impact assessment of the project.

21.02.2011

Obtaining of the final comments from the Regional Director to the report after the Commission’s analysis.

VI-VIII .2011

Elaborating of the the supplement to  the report.

24.08.2011

Submission of the supplement  to the report to the Regional Director of Environmental  Protection. According to the Regional Director, the finishing of the environmental decision making  is expected  at  23.11.2011.

21.11.2011

The Regional Director of Environmental Protection has announced start of the procedure of the project environmental impact assessment with public participation. The new date for issuing of the environmental decision is fixed on 15.02.2012. 

21.03.2012

On  21 March  2012, the  Regional Director of Environmental  Protection in Kielce  issued the environmental decision  for realization of Kielce  Airport  in all its phases of construction and development. Decision is not final. 

29.06.2012

On August 31st , 2012 we expected General Director of Environmental Protection in Warsaw to submit a decision on appealed the environmental decision for Kielce Airport.

10.09.2012

On Septermber 10th, the General Director of Environmental Protection in Warsaw informed that the deadline for considering the appeal against the environmental decision for Kielce Airport was moved to 29 October 2012r.

30.10.2012

The deadline for considering the appeal against the environmental decision for Kielce Airport  was  moved by  the General Director of Environmental Protection in Warsaw, to 14 December 2012r.

19.12.2012

The deadline for considering the appeal against the environmental decision for Kielce Airport  was  again moved by  the General Director of Environmental Protection in Warsaw, to 28 February 2013r.

1.03.2013

The deadline for considering the appeal against the environmental decision for Kielce Airport  was  again moved by  the General Director of Environmental Protection in Warsaw, to 30 April  2013r.

7.05.2013

The deadline for considering the appeal against the environmental decision for Kielce Airport  was  again moved by  the General Director of Environmental Protection in Warsaw, to 31 May  2013r

 

 
 
   
 